Update on Project

The Capital Project is progressing. If you have been to the school lately, you will see the STEAM addition going up next to the HS gym. (projected completion date of December 2023). It promises to be an incredible learning space when it is finished. The MS locker rooms, Ag suite and Small Engine area are in their final stages of completion. The hope is for students to be in those renovated areas by February or March of 2023.

Update on Capital Project - 10-13-21

LCSD Board of Education Meeting - 
2020 Capital Improvement Project
 
Introductions
  • Turner Construction - 
    • Michelle Miller - Preconstruction
    • Mark DiMartile - Project Superintendent
  • HUNT E|A|S -
    • Shannon Davis - Project Manager
    • Jake Zurlick - Project Architect
Design Process Update - 
  • Field Work
  • Meetings with District staff & end users
  • Board Presentations
  • Pre-referendum planning
  • Successful Vote
  • Design phase began in January
    • Field Trips
    • Design meetings with district & end users: STEAM, Nurse, Athletics, ES Staff, Facilities
    • Classroom observation
  • September SED submission
Major Scope Items (K12 Building) - images with what the space will look like
  • Nurse's Suite
  • Middle School Locker Room
  • Innovation Center Overall Plan
  • Maker Space (various views)
  • Wood Shop (various views)
  • Metal Shop (various views)
  • Outdoor Images of Innovation Center
  • Small Engine (Various Views)
  • Ag Lab (Various Views)
  • Ag Canopy
  • Elementary - STEAM Room
  • Multi-purpose Canopy/ES STEM outdoor classroom
  • Fuel Island
  • Turf Field
  • Miscellaneous Areas of Scope
    • Asphalt Replacement
    • Fire Alarm Upgrades
    • Sidewalk Replacement
    • Water Well Upgrades
    • Pre-K Playground
    • Toilet Room Upgrades
    • Casework Replacement
    • Chalkboard Replacement
    • Theater Rigging Improvements
    • Hydronic Pump & Boiler Replacement
    • Classroom Ventilation Improvements
    • Music Suite Sound Upgrades
    • VCT Replacement
    • Athletic Field Scoreboard Replacement
    • MS Gym Backstop Replacement

Project Budget

Current Market Conditions & Trends
  • Project Team reaching out to vendors and suppliers regarding material lead times
  • Pricing Trends
  • Current indications are pricing is not declining.
Next Steps
  • September/October Activities
  • November Activities
  • December Activities
  • Spring 2022